Details GARDNER
ZEMKE’S work will include the supply and installation
of four (4) 5,000 HP 56 cfs pumping units, two (2) 2,500
HP 28 cfs pumping units, and two (2) 1,250 HP 14 cfs pumping
units along with all associated manifold piping, motor operated
valves, unit cooling water systems, compressed air systems,
and motor control equipment. GARDNER ZEMKE will also install
72” and 84” diameter steel manifold piping in
the plant and 72” and 84” cement lined steel
line pipe outside of the plant for the suction and discharge
piping. Other features include the supply and installation
of two (2) overhead bridge cranes, an electric traction elevator,
and a 39’ diameter spherical steel ASME pressure vessel
for the discharge pipeline.
This project was a negotiated procurement,
which is scheduled to begin in July 2004 and complete in
October 2008. Our team also includes Subcontractors NIELSONS
/ SKANSKA for pipeline and steel manifold construction, CHICAGO
BRIDGE & IRON (CBI) for the 39’ diameter air chamber
construction, and THE FLOWSERVE PUMP DIVISION for the pumping
units and motors.
|