GENERAL MILLS CEREAL PLANT
Albuquerque, NM
Return to the Industrial projects
Contract Amount:
Owner:
Prime Contractor:
$ 5,600,000 (Electrical)
GENERAL MILLS
GARDNER ZEMKE COMPANY

Overview
The General Mills Cereal Plant in Albuquerque ranks as one of the largest construction projects to come to New Mexico in years. The plant has its own railroad spur and is one of the largest users of electricity in Albuquerque.

This was the first horizontally designed plant for General Mills, and they brought engineers from all over the country to observe it. This was also the largest computer automated project in the country at the time.

Details
To facilitate construction in May 1991, GARDNER ZEMKE completed the site’s temporary power consisting of four power locations and a 500KVA service feed by 12,470 volts, which is definitely not typical of temporary service. Work also included the site telephone utility, with manhole.

In 1992 GARDNER ZEMKE’S Electrical Division signed additional contracts for the processing and packaging of cereals. The work consisted of instrumentation and electrical, labor intensive small conduit, and associated wiring. The GARDNER ZEMKE Electricians completed the start-up in two weeks where the Owner had anticipated a two to three month schedule. Because of General Mill’s high confidence in GARDNER ZEMKE, we maintained a presence at the plant after it’s initial completion.

We worked on a T&M basis performing many tasks modifying the existing plant. Each task required a NTE estimate prior to beginning work, then costs were closely monitored and reported to plant personnel to insure that budgets were met. The tasks included everything from running additional lighting to control system upgrades.

In 1997 GARDNER ZEMKE began one of the major tasks at General Mills known as Delivery System Replacement Project. In 1998 work started at an extension to the north side of the plant called the Jetzone Building. A 120’ by 30’ slab was poured and the necessary grounding was installed. Three 3” conduits with 400 MCM wire, running approximately 50-0’ across the plant was provided. GARDNER ZEMKE was also responsible for all electrical connections to equipment that was brought in from another General Mills facility.

In 1999 the plant upgraded and expanded one of their production lines and installed a robotic conveyor system. The work included the electrical disconnection of the existing equipment and the removal of existing conduit and wire, then installing the new equipment and running new conduit and wire, and testing everything out. The robotic conveyor was designed to take the place of several forklifts, which carried packaged cereal products to the truck docks. The conveyor system was completely computerized and designed so each section works independently. The boxes of cereal move along the conveyor while sensor eyes regulate their speed and movement. GARDNER ZEMKE was responsible for the electrical installation and testing on this project.

© 2005 Gardner Zemke. All right reserved.