|
Details This multifaceted project
included the demolition of two existing 1500kW diesel generators,
two steam boilers, and all associated ducting and cabling. The
equipment was replaced with two 4MW dual fuel turbine generators
and all appurtenances including new heat recovery steam boilers,
evaporative coolers, lube oil coolers, exhaust and inlet stacks,
and new de-aerator. Demolition included two switchgear lineups
replaced with 5kV generator switchgear and 15kV paralleling switchgear.
Electrical installation included 5,000 KVA transformers, unit
substation, motor control centers, etc. The plant was updated
with a SCADA system with automatic controls. Most of the work
was performed with the plant fully operational with only brief
outages. Major changes were required to the existing structure,
including relocation of roof members to accommodate new equipment,
erection of a new mezzanine and access grating platforms, and
construction of a new addition to the soundproof control room.
This project also involved replacing three existing
300kW generators with three 600kW generators. It included the
construction of a new generator building with three 600KW generators
and paralleling switchgear. Also included is the expansion of
the medical center’s electric room, which houses the new
emergency switchgear, over 7,500’ of 250 MCM, up to 4-conductor
armored cable, and 35,000’ of 500 MCM, 600V cable. |