|
Details Construction on the primary site electrical distribution
system for the Bernalillo County Detention Center consisted of
the installation of primary, normal and emergency power and 15
kV distribution system. Installation consists of underground
ductbank, manholes, 15 kV switchgear, 15 kV sectionalizing switches,
15 kV paralleling switchgear, two 1850 kW, generators, designed
to have six, 15 kV transfer switches, pad-mounted transformers,
480-volt switchgear, and overhead power line. The distribution
system is a loop feed with overhead power line with the ability
to parallel with main utility source. Also installed as part
of this project was the high mast lighting for the site.
The duct bank portion of this project included the installation
of 16-way 6”, 12-way 6”, 8-way 6”, 6-way 6”,
8-way 4”, 4-way 4” duct banks, site lighting conduit,
six new manholes, poured in place high-mast pole bases and high-mast
lights. |