Details The
construction of the 115 kV WTA Substation for Los Alamos National
Laboratory consisted
of site preparation, fencing of the project site, concrete piers,
foundations and vaults, duct bank, erection of switchyard structural
steel, and construction of a pre-engineered metal control building.
The electrical equipment installed includes a 56 MVA, 115 kV
power transformer, three 115 kV SF6 gas circuit breakers, ten
115 kV switches, a 16’ x 52’ walk-in switchgear house,
which weighs in excess of 90,000 lbs., and a 115 kV overhead
aluminum ring bus.
|