  • Project:
  • Strategic Computing Complex
  • Location:
  • Los Alamos National Laboratory – Los Alamos, NM
  • Scope of Work:
  • Computer Facility – Complete MEP
  • Owner:
  • U.S. Department of Energy/Los Alamos National Laboratory
  • Prime Contractor:
  • Hensel Phelps Construction Company
  • Architect/Engineer:
  • HDR, Inc.
  • Contract Value:
  • $22,694,825 (MEP)

Project Summary

This design-build project required the complete separation of classified and unclassified mechanical and electrical systems for security purposes including HVAC systems, as well as secured and non-secured power and communications. The 303,000 square foot facility is fed by two separate 15kV underground services, which connect to two outdoor 15kV SF6 switchgear lineups with the capacity to serve 11 megawatts of power for existing and future loads.

 The 15kV outdoor switchgear lineups connect to seven installed  15kV-480/277 volt indoor double- ended unit substations and one 15kV-4, 160 volt substation for connected building and computer loads. The existing computer loads are connected through three 1,670 KVA rotary UPS systems and future space and system capacity has been provided for three additional 15kV-480/277 volt double-ended substations and nine 1,670 KVA rotary UPS systems.

  • spe_img1
  • spe_img2
  • spe_img3
Our Projects
  • CAB Hangars Fort Bliss
    CAB Hangars Fort Bliss

    Fort Bliss Army Base – El Paso, Texas

  • Durango Pumping Plant
    Durango Pumping Plant

    Durango, Colorado

  • Exterior Communications Infrastructure Modernization
    Exterior Communications Infrastructure Modernization

    Sandia National Laboratory – Albuquerque, New Mexico

  • Electromagnetic Vulnerability Assessment Facility
    Electromagnetic Vulnerability Assessment Facility

    White Sands Missile Range – New Mexico

  • Fort Bliss Replacement Hospital
    Fort Bliss Replacement Hospital

    Fort Bliss Army Base – El Paso, Texas

  • GSU Transformers K19A and K20A Replacements
    GSU Transformers K19A and K20A Replacements

    Grand Coulee Third Power Plant – Grand Coulee, WA

  • Grand Coulee Left and Right Power Plants
    Grand Coulee Left and Right Power Plants

    Grand Coulee, Washington

  • Infantry Brigade Combat Team – Company Operations Facility
    Infantry Brigade Combat Team – Company Operations Facility

    Fort Bliss Army Base – El Paso, Texas

  • Joint Computational Engineering Laboratory
    Joint Computational Engineering Laboratory

    Sandia National Laboratory – Albuquerque, New Mexico

  • National Enrichment Facility Substation
    National Enrichment Facility Substation

    Eunice, NM

  • National Security Sciences Building
    National Security Sciences Building

    Los Alamos National Laboratory – Los Alamos, NM

  • Unaccompanied Enlisted Personnel Housing – BCT 1
    Unaccompanied Enlisted Personnel Housing – BCT 1

    Fort Bliss Army Base – El Paso, Texas

  • Union Pacific Railroad – Fueling Facility, Block Swap Yard and Intermodal Facility
    Union Pacific Railroad – Fueling Facility, Block Swap Yard and Intermodal Facility

    Lordsburg Subdivision – Strauss, NM

  • MESA Weapons Integration Facility
    MESA Weapons Integration Facility

    Kirtland Air Force Base – Albuquerque, New Mexico